Ceuta plugs into mainland Spain: a 58 km cable to leave diesel behind
Since 10 August 2026, two cables under the Strait of Gibraltar have tied Ceuta to the mainland grid. Red Eléctrica expects up to 87% of its power to arrive emission-free.

On 10 August 2026, Ceuta plugged into the rest of Spain's electricity grid for the first time. The link runs 58 kilometres under the Strait of Gibraltar, at depths of up to 900 metres, from the bay of Algeciras to the North African city. Until that day, the power used by its 83,595 residents came almost entirely from diesel engines inside the city itself. On 21 September, grid operator Red Eléctrica confirmed the link was finished, energised and had already prevented at least one power cut.
- Ceuta ran as an isolated power system, almost entirely on diesel.
- Two 132-kilovolt cables now cross the Strait from the Algeciras area to the new Virgen de África substation.
- Red Eléctrica estimates that up to 87% of the city's demand can be met with emission-free electricity, avoiding about 300,000 tonnes of CO₂ a year.
- Commercial power trading between the two systems is due to start on 1 December 2026, according to Red Eléctrica and the deadline set by Royal Decree-law 18/2026.
A city that ran on engines
The numbers before the cable are stark. According to Red Eléctrica's March 2026 figures, Ceuta used about 206 gigawatt hours of electricity in 2025, 4.8% more than the year before. Nearly all of it came from diesel engines. Gas turbines supplied a sliver, and solar panels made up less than 0.1% of the city's 91 megawatts of installed capacity.
Demand peaked on 9 July 2025 at 678 megawatt hours in a single day.
Nothing changed in 2026 while the cable was still being tested. Red Eléctrica data up to 31 August, reported by the trade outlet El Periódico de la Energía, show that Ceuta generated 146,906 megawatt hours in the year, 99.9% of it from diesel. Renewable output was zero.
That dependence was expensive. Red Eléctrica's own website described Ceuta as the only part of Spain without green energy. Burning diesel in a small, isolated system costs more, and the national electricity system covers the difference. And when one of the generating units failed, there was no neighbour to call on.
Melilla, Spain's other North African city, is still in that position. Both cities have been run as separate systems from the Balearic Islands control centre, each with its own power plant. The Balearics have already made the journey Ceuta has just completed: the islands have been linked to the mainland by a subsea cable since 2012.
From the drawing board to the seabed
Plans to tie Ceuta into the mainland grid are more than a decade old. The route stalled from 2016 because of opposition from environmental groups and the town council of La Línea, as analyst Ignacio Urbasos noted in 2021 for the University of Navarra's Global Affairs programme. That year Spain's competition and markets regulator, the CNMC, classed it as a singular project.
The design was reworked to shrink its footprint. The milestones since then:
- 11 June 2024: construction begins, with authorisation from the Ministry for the Ecological Transition and a favourable environmental impact statement.
- August 2025: Endesa receives two 40 MVA transformers, each weighing more than 53 tonnes, at the port of Ceuta for its distribution substation.
- September 2025: the first cable reaches the Ceuta coast.
- November 2025: Red Eléctrica completes the Virgen de África substation, its first transmission facility in the city, and the cable ship Giulio Verne lays the second cable.
- December 2025: transmission works are finished.
- 13 March 2026: the first circuit is energised.
- 30 June 2026: the distribution equipment is switched on.
- 22 July 2026: synchronisation tests are passed.
- 10 August 2026: final connection.
Both circuits carry alternating current at 132 kilovolts. On the mainland side, the line leaves the Algeciras substation and runs underground for about 9.2 kilometres through San Roque and La Línea de la Concepción. In Ceuta, the buried section up to the substation is 1.7 kilometres long.
Making subsea cables has become an industry in its own right. In Scotland, a former oil platform yard has been converted to produce them, as we reported in Nigg now makes cables for wind power.
To bring the cables ashore without touching the beaches, engineers used horizontal directional drilling: a narrow tunnel that carries the cable from land to several hundred metres out to sea. This kept the works clear of bathing areas and protected coastal species, and the marine route was adjusted to coexist with local fish farms and fishing grounds, according to Red Eléctrica.

In Ceuta, the new Virgen de África substation uses gas-insulated switchgear, known as GIS: all the equipment sits inside a building, takes up less land and is barely visible from the street. Next to it, Endesa's local distribution company, Empresa de Alumbrado Eléctrico de Ceuta, spent 9.5 million euros on a second substation that steps the voltage down from 132 kilovolts to the 15 to 20 kilovolts used on city streets.
The whole link cost more than 200 million euros, according to Spain's Secretary of State for Energy, Joan Groizard, speaking when the first cable came ashore in September 2025.
The most important energy infrastructure in Ceuta's recent history.
Joan Groizard, Secretary of State for Energy, September 2025
What has changed, and what comes in December
Red Eléctrica's statement of 21 September 2026 sets out the first practical effect. The two systems are synchronised, and if Ceuta's generators fail, the mainland can cover the city's demand instantly. The company says the link has already backed up the city during a recent incident and avoided lost supply.
The second effect arrives with commercial scheduling. So far, the local plant has kept producing almost all the electricity used in Ceuta. From 1 December, the system operator will be able to schedule exchanges with the mainland market, so power arriving through the cable can replace output from the engines. Several outlets had reported 1 November as the start date; Red Eléctrica's statement sets 1 December.
The legal basis is the first transitional provision of Royal Decree-law 18/2026 of 29 June, later ratified by Congress. It applies to Ceuta the operating rules used for the Balearic link in 2012 and keeps the existing plant as a reserve for times when a cable is down for maintenance. The decree spells out the aim: cut the use of fossil fuels at Ceuta's plant and let the city draw on renewable generation from the mainland.
Red Eléctrica's estimates, reported by Ceuta Actualidad and other outlets, are:
- Up to 87% of Ceuta's demand met with emission-free electricity from the mainland.
- About 300,000 tonnes of CO₂ avoided every year.
- Savings of close to 30 million euros a year for the national electricity system, which no longer has to pay the extra cost of burning diesel in an isolated grid.
In 2025, Spain as a whole produced 55.5% of its electricity from renewables, according to the same Red Eléctrica report. That is the mix now starting to flow through the cable, in line with a global trend in which renewables have overtaken coal.
The link also opens doors for the local economy. Data centre company Templus has announced that CEU01, Ceuta's first data centre, will open in the port on 15 December running on 100% renewable power. In Melilla, insurer Pelayo is also betting on technical talent, as we reported in Melilla wants engineers.
The scare of 21 October
The start-up has had one setback. At 9.39am on 21 October 2026, an incident at the Algeciras substation disconnected the interconnector cables. Ceuta's diesel units were still covering nearly all demand at the time; the disturbance tripped the plant's protection systems and the whole city lost power for close to an hour, elDiario.es reported. Endesa restored supply in 55 minutes, and Red Eléctrica said the entire high-voltage system was reconnected by 10.34am.
Red Eléctrica acknowledged that the incident in Cádiz province does not on its own explain what happened in the city, and both companies opened an investigation.
What still needs to happen
The first task is to start commercial scheduling on 1 December and check in Red Eléctrica's monthly data how far diesel output falls. The second is to close the investigation into the October blackout and fine-tune the protection systems on both sides of the Strait. The third is regulatory: the decree describes a transitional regime that lasts "until a new regulatory framework is defined" for dispatchable generation in Ceuta, which means deciding what role the current plant will play in the medium term.
Then there is Melilla, which will keep running as an isolated system. Other remote places are trying different routes away from diesel, such as the Galápagos with its geothermal survey.
A detail you may not know
Until this project, neither Ceuta nor Melilla had a single metre of electricity transmission grid, only local distribution networks and a power plant. The Virgen de África substation is the first transmission facility Red Eléctrica has built in Ceuta, and it takes its name from the city's patron saint.
Further reading
Go further
- Web · Red EléctricaLa interconexión ya conecta el sistema eléctrico peninsular con Ceuta
La nota oficial con el calendario completo de energización y la fecha del intercambio comercial.
- Blog · Ignacio Urbasos, Global Affairs (Universidad de Navarra)Conexión eléctrica entre Ceuta y la península: un asunto de seguridad energética y medioambiental
Explica por qué el proyecto estuvo años parado y su valor estratégico en el Estrecho.
- Web · Red EléctricaNon-peninsular systems
Cómo funcionan los sistemas eléctricos de Baleares, Canarias, Ceuta y Melilla.
- Web · XatakaCeuta está a punto de dejar atrás los generadores diésel
Repaso divulgativo con el trazado completo, tramos terrestres incluidos.
- Web · Xataka MóvilDos nuevos cables submarinos conectan a Ceuta con Europa
Cuenta cómo el buque Giulio Verne tendió el segundo cable en noviembre de 2025.
- Web · EndesaLa subestación que conecta Ceuta con la península por el cable submarino
Detalles de la subestación de distribución y de sus dos transformadores de 40 MVA.
Sources
- Red Eléctrica: La interconexión ya conecta el sistema eléctrico peninsular con Ceuta (21/09/2026)
- BOE: Real Decreto-ley 18/2026, de 29 de junio (disposición transitoria primera)
- Red Eléctrica: La demanda de energía eléctrica en Ceuta aumenta un 4,8% durante 2025
- Ceuta Actualidad: Fin del aislamiento eléctrico, Ceuta ya está conectada a la Península
- elDiario.es: Ceuta sufre un apagón de cerca de una hora en toda la ciudad
- El Periódico de la Energía: Ceuta dice adiós al diésel
- Endesa: subestación que conecta Ceuta con la península