Chone will stop drinking from its river: new water system is 82% complete
The project bringing water from the Río Grande dam to the Manabí town went from 32% to 82% complete in seven months and will lift coverage from 70% to 98%.

On 5 November, twenty water trucks criss-crossed Chone from six in the morning until eleven at night. The town's main distribution pipe had burst after days of heavy rain, and 60% of homes in this inland canton of Manabí, on Ecuador's Pacific coast, were left with an unreliable supply, according to El Universo. A week later, a few kilometres from those neighbourhoods, the project designed to end that routine reached 82% completion.
Ecuador's Ministry of Infrastructure and Technology (MIT) reported on 12 November that the rebuild of Chone's drinking-water system had hit that mark. It is the third phase of the canton's water and sanitation master plan, funded with more than $24 million that the national government transferred to the municipality under a subsidiary agreement. The core change fits in a single line of the official bulletin: the town will stop drinking straight from the river.
- Chone's drinking-water project went from 32% physical progress in April to 82% on 12 November 2026.
- Water will arrive from the Río Grande reservoir through a new supply main, instead of being drawn from the Chone river.
- The works include 330.84 kilometres of pipe and about 7,975 new water meters.
- Projected coverage rises from 70% to 98% of the population served.
- Investment exceeds $24 million, transferred to the municipality by the national government.
A river that does not always run clean
Chone lives alongside its river. The town grew in a valley in northern Manabí where water is plentiful in the rainy season and scarce in the dry months, and where several rivers meet before heading for the sea. In 2024, its 128,166 residents spent months under a disaster declaration because of flooding, with losses of about $45 million according to municipal figures cited by Primicias. In the worst recent winters, water covered up to 90% of the streets in the town centre.
That is the paradox people in the province know well: a town that floods often and yet cannot keep clean water flowing from its taps. The explanation lies in how water is collected and distributed.
For decades, the supply system drew water directly from the river channel, treated it at an ageing plant and pushed it through networks that in some stretches were laid on the riverbed itself.
That design had a weak spot every resident understands. When heavy rain falls, the river turns brown with silt and turbidity soars. Pumps have to be switched on and off repeatedly to keep sediment out of the treatment plant, and each manoeuvre puts stress on the pipes. That is what happened in early November, according to the explanation given by mayor Leonardo Rodríguez and reported by El Universo: El Niño rains raised both the flow and the murkiness of the river, the manoeuvres multiplied and the main pipe gave way.
The response was an emergency one. The municipality split the trucks into two groups of ten, one for each bank of the river, and sent them to neighbourhoods such as Santa Martha, La González, Los Naranjos 1, Potrerillo, San Cayetano and Los Choferes. Repairs through an alternative line were expected to take 48 to 72 hours.

The MIT bulletin describes the problem plainly: supply has been failing for more than three decades, and during the rainy season the river's turbidity makes collection and treatment difficult. The new project starts from that diagnosis and moves the point where the water comes from.
Where the water will come from
The centrepiece is a new supply main from the Río Grande dam, a reservoir built upstream of the town. The dam is part of the Chone Multipurpose System, an $80 million project designed to tame floods on the Río Grande, the tributary that poses the greatest threat to the town, and to store water. For years Chone had that reserve a few kilometres away and still drew from the river. Phase three of the master plan fixes that disconnect.
Water held in a reservoir arrives calmer and clearer than water rushing down a swollen river, which cuts the sediment load the treatment plant must handle. The ministry put it this way in its 12 November bulletin:
"Chone will no longer depend on drawing water directly from the river"
Bulletin No. 843, Ministry of Infrastructure and Technology
Alongside the new main, the project modernises the treatment plant, rebuilds and extends the distribution networks with 330.84 kilometres of pipe, and installs about 7,975 meters. When the mayor announced the transfer of funds at a ceremony marking Chone's 131st anniversary as a canton in July 2025, he described a four-module plant able to treat 320 litres per second and a neighbourhood-by-neighbourhood renewal of the networks, according to the Manabí newspaper El Diario.
Flood control has advanced on a separate track. Between 2024 and 2025, the Manabí provincial government and the environment ministry cleared and channelled more than 31 kilometres of the Chone and Garrapata rivers. In March 2025, provincial prefect Leonardo Orlando told Primicias that the work had paid off and that the town had not flooded from overflowing rivers that winter.
The goal repeated across every document is easy to state and hard to deliver: water every day, around the clock, for the urban population.
Fifty points in seven months
The progress figures show a project that has picked up speed. On 8 April 2026, during an earlier inspection, phase three of the water system stood at 32% physical progress, with 210 jobs created and a projected service life of 25 years, according to KCH and El Diario. On that visit, regional undersecretary Gerardo Giler summed up the aim in a sentence residents went on to repeat:
"Chone is going to have water continuously"
Gerardo Giler, regional undersecretary, April 2026
By 12 November the figure was 82%. President Daniel Noboa and infrastructure minister Roberto Luque toured the works that day, according to the MIT and El Oriente. The bulletin does not yet set a handover date.
Beneficiary numbers vary between documents and are worth reading carefully. In April, officials spoke of 131,000 people served by the system. The November bulletin refers to more than 54,000 direct beneficiaries. The gap probably reflects the difference between direct users of the new networks and the total population served, but the ministry has not explained it.
The other half of the plan: sewers and drainage
Drinking water is only part of the story. The same master plan includes a parallel sewerage and storm-drain project financed by Banco de Desarrollo del Ecuador (BDE), the state development bank, which was 92% complete in April. According to figures presented then, that work adds 35.86 kilometres of water network, 37.80 kilometres of sanitary sewer, 9.46 kilometres of storm drains and 506 drain inlets across the town centre, San Felipe, El Paraíso and Tacheve. It cost $13.9 million, of which $8.1 million is non-repayable, and created 481 jobs.
BDE manager Carlos Rivera said in April that with that project water and sewer coverage would be "very close to 100%". Shopkeeper Emma Minaya put it her own way to reporters from El Diario: "Thank you for giving Chone back its hope."

The link between clean water and public health is direct. A system that relies on a muddy river forces households to store water in tanks and buckets, where it is easily contaminated, and pushes many families to buy from trucks. Officials list among the project's aims reducing health risks from poor-quality water and keeping supply steady through the rainy season, precisely when it fails most often.
What remains, and what this rainy season will test
Eighteen percentage points of work remain, and the rainy season is expected to be long. Ecuador's national weather and hydrology institute has kept heavy-rain warnings in place for Manabí and the rest of the coast through November, and the breakdown earlier in the month showed that the current system copes poorly with such episodes. Until the new supply main comes into service, Chone will still depend on its river.
Other tasks have nothing to do with concrete. Installing almost eight thousand meters will change how the service is billed, a sensitive issue in a canton that in 2025 approved a bylaw updating water tariffs from 2026. And running a modernised plant requires trained staff and steady maintenance, which the municipality will need to fund once the construction money runs out.
There is also the question of timing. The ministry's figures show that the project gained fifty points of progress between April and November, roughly seven points a month. If that pace held, the physical works could be finished within the first quarter of 2027, but no official has committed to a date, and the final stretch of any water project, testing the network, connecting homes and commissioning the plant, is often the slowest.
For residents, the test will be simple. In July 2025, Dolores Pinargote, a mother from Chone, told El Diario: "It is a historic moment for us, because water is what we long for most." The project is now less than a fifth of the way from meeting that expectation.
Other water projects in Ecuador show the kind of change on offer. In Santo Domingo de los Tsáchilas, a 17-kilometre pipeline now brings water from Otongo to the city at 500 litres per second, and on the Santa Elena peninsula a coastal community stores rainwater beneath its riverbed to supply 40,000 people. In Manabí, the same province that this year brought the world to its table with Chone's famous cheese, reliable tap water is still an unpaid debt in several cantons.
For readers who want to prepare for this season's rains, our newsroom has published a guide to what is known about El Niño in Ecuador and what every household can do.
The detail you may not know
The word at the heart of the project is "aducción", the Spanish engineering term for a supply main: the pipe or channel that carries raw water from its source, in this case the Río Grande reservoir, to the plant where it is made safe to drink. In Chone that single component captures the difference between the old system and the new one. Water will no longer enter the town from a channel that turns muddy with every downpour; it will come from a reservoir that is more stable and acts as a first, natural filter.
Further reading
Go further
- Web · Ministerio de Infraestructura y TecnologíaChone más cerca de contar con agua potable
El boletín oficial con los componentes de la obra y las cifras de cobertura.
- Web · Secretaría General de Comunicación de la PresidenciaObras para fortalecer el agua potable y el saneamiento en Chone
Resume las obras de agua y saneamiento en marcha en el cantón.
- Web · El UniversoChone sin agua: 20 tanqueros abastecen a los barrios afectados
Muestra por qué la ciudad necesita dejar de captar agua del río.
- Web · PrimiciasLas tres razones por las que Chone no colapsó en el invierno
Contexto sobre las obras de control de inundaciones y la represa Río Grande.
- Web · El DiarioObras de agua potable apuntalan la productividad en Chone
El punto de partida: la obra estaba al 32 % en abril de 2026.
Sources
- MIT: Chone más cerca de contar con agua potable (82 % de avance)
- El Oriente: reconstrucción del sistema de agua potable de Chone alcanza el 82 %
- KCH: Chone más cerca de contar con agua potable
- El Universo: 20 tanqueros abastecen a barrios de Chone
- El Diario: avance de obras de agua en Chone (abril de 2026)
- Primicias: tres razones por las que Chone no colapsó