A judge halted the port's expansion onto El Murciélago beach, in Manta
A citizens' collective won a court order that stopped the expansion of Patio 600, a port project that was advancing onto three hectares of Manta's best-known beach. The case is still open, and each side insists it is in the right.

- The Citizens' Commission for the Defense of El Murciélago Beach sued over the Patio 600 expansion in September 2026 and won a court order halting the work.
- The USD 2.3 million project aimed to add roughly three hectares of beachfront to the Manta Port Terminal, a subsidiary of Chile's Agunsa.
- A biologist consulted by Primicias estimates about 4,000 cubic meters of sand have already been removed from a sea turtle nesting area.
- The city government says the zone is a protected conservation area that cannot be touched without its permits.
On El Murciélago beach, Manta's most visited stretch of sand, swimmers share the shore with one of Ecuador's busiest ports. Roughly 90% of all vehicles imported into the country pass through it, according to the Ministry of Infrastructure and Transport. For years, that coexistence worked quietly. This year it turned into open conflict, when the Manta Port Terminal (TPM) announced it would expand its storage yard, known as Patio 600, onto about three hectares that include part of the beach and a strip next to it.
From a USD 2.3 million project to a citizens' lawsuit
The expansion was announced in August 2026 as part of a public-private partnership between the Manta Port Authority (APM), which represents the state, and TPM, the subsidiary of Chile's Agunsa that has run the terminal since 2016 under a 40-year concession. The declared budget for the project is USD 2.3 million. The official justification is that the port needs more storage space to keep up with trade that keeps growing. Between January and August 2026 alone, TPM moved more than 80,000 imported vehicles.
In mid-September, the Citizens' Commission for the Defense of El Murciélago Beach, a collective born out of public assemblies of neighbors and local merchants, filed a protective action with a precautionary measure attached. The court granted it and halted the work while the case is decided on its merits.
The collective's lawyer, Trajano Andrade, argues that after 71 days of proceedings, the violation of nature's rights has already been demonstrated, and he's asking for the work to be banned permanently. In his reading, the project aims to take over roughly 30,000 square meters of beach that, he says, belong to the city of Manta.

Three positions, three readings of the same stretch of sand
The Manta Port Authority answers that the project has an approved environmental permit and includes prevention, mitigation and compensation measures, and that it respects legal certainty and whatever courts ultimately decide. The agency presents the expansion as a logistical need, since storage demand already outstrips current capacity. Along the same lines, deputy transport minister Bryan Andrade said in September there's no environmental damage, and that the project is meant, if anything, to prevent future harm.
The city government sided with the collective. Mayor Marciana Valdivieso said in September that this strip of beach is designated in municipal planning as a Conservation and Sustainable Use Area (ACUS). That means any work there requires city permits that, in her account, were never obtained.
This isn't the first time a local government and Manta's port have clashed over this exact stretch of beach.
What a biologist who measured the site found
Among the interested parties, biologist Iván Murillo offered an independent technical read. By his observations, roughly 4,000 cubic meters of sand have already been removed from an area that serves as a nesting site for sea turtles and a resting spot for birds. The removal has also shrunk the beach's recreational space.
Murillo also challenges the project's environmental permit, which he says contains errors in land-use classification, in the coordinates listed, and in the description of the materials to be used.
This isn't the first round of this fight, either. In July 2019, during a technical meeting with then-mayor Agustín Intriago (assassinated in 2023), representatives from TPM and APM had already floated a similar expansion. Intriago rejected it with the same argument the city repeats today: that land belongs to the municipality, since it was reclaimed from the sea.
Seven years later, the underlying disagreement is essentially the same.
Why the legal argument carries so much weight here
The collective's lawsuit is built on the rights of nature, a legal concept Ecuador's 2008 Constitution recognized in a way that was pioneering worldwide. It allows any person or group to sue on behalf of an ecosystem without having to prove direct personal harm. The same legal foundation has been used in other environmental cases across the country to halt construction or extractive activity while a judge weighs whether a protected ecosystem faces a real risk.
The action was accepted. And the precautionary measure has held for 71 days by the plaintiff lawyer's own count, which suggests the argument carried at least enough weight to stop the machinery while the case gets a full review.
That doesn't amount to a final ruling, though. A precautionary measure is, by definition, a preventive pause: it protects the status quo while the process moves forward, but it can be reversed if the judge ultimately concludes that TPM's environmental permits were valid and sufficient.
What you can do
- If you're visiting Manta, you can follow the state of El Murciélago beach and the construction work through local press and the official accounts of the city government and the Port Authority.
- Any Ecuadorian citizen can file a similar protective action when they believe a project harms an ecosystem, without needing to be the directly harmed party: it's a right the Constitution recognizes broadly.
- Anyone following port or coastal infrastructure issues in the country might find it useful to compare this case with similar ongoing disputes, like the one over where Guayaquil's next airport should go.
What's next, and what's still unknown
For now, according to the plaintiffs' lawyer, the work remains paralyzed. The Port Authority, in a statement issued on November 13, didn't detail the exact status of the work or respond directly to that claim.
There's also no ruling on the merits yet. What exists is the precautionary measure that halted construction while the judicial process moves forward. The outcome hinges on what is still open: the final court ruling, whether TPM's environmental permits hold up to scrutiny, and the city's final position on whether it will authorize any work in an area it considers protected.
The case shows how Ecuador's system of checks operates when a construction project collides with public space. A collective of neighbors took its complaint to court and got a judge to halt a multimillion-dollar project while the case is reviewed. All three parties (the port, the national government and the city) had to lay out their arguments publicly.

For the local economy, the standoff matters. The Manta Port Terminal is, alongside the scenic boardwalk and the fishing industry, one of the engines that sustains much of the city's employment, and any brake on its expansion carries a real opportunity cost. El Murciélago beach, for its part, has been for decades the main public recreation space for people from Manabí and one of the draws that bring visitors from across the province to Manta on weekends and holidays. Because of that dual value, economic and recreational, neither side seems willing to give ground before a judge settles the matter.
The dispute over Guayaquil's future airport, between the Taura and Daular proposals, shows that this kind of standoff between local governments and port or airport infrastructure projects isn't unique to Manta. In the same province of Manabí, other water and infrastructure projects, like the new drinking-water network that already covers 82% of Chone, are moving forward without this kind of legal stumble. The conflict at El Murciélago appears tied to the particulars of that one beach more than to any broader pattern across the region.
To go deeper
- The Patio 600 expansion in Manta, a legal battle between port and environmental interests, Primicias' full report on the case.
- Manta Port Authority, the official channel of the agency that runs the port.
- Manta Port Terminal (TPM), the concession operated by Chile's Agunsa group.
The detail you might have missed
The current fight over Patio 600 isn't new. Back in 2019, under a different mayor and a different balance of power, the city of Manta had already rejected an almost identical proposal to expand the port onto the same beach, using the same argument it uses today, seven years and a pandemic later.
Go further
- Web · PrimiciasAmpliación del Patio 600 en Manta, una batalla legal entre intereses portuarios y ambientales
El reportaje completo del caso, con la cronología de la demanda.
- Web · APMAutoridad Portuaria de Manta
El canal oficial de la entidad estatal que administra el puerto.
- Web · TPM / AgunsaTerminal Portuario de Manta (TPM)
El sitio de la concesionaria que opera la terminal desde 2016.
- Web · The Positive WayLa disputa por el futuro aeropuerto de Guayaquil
Un caso similar de choque entre infraestructura e intereses locales.