Twelve more metres of water before El Niño: Hidroituango finally hits its design level
The reservoir of the Antioquia power plant reached elevation 420, its original design level, on 9 November, storing about 187 GWh of extra energy for the driest months of El Niño.

On Monday 9 November, the Cauca River reached a line engineers had drawn on their plans more than a decade ago. The reservoir behind Hidroituango, in northern Antioquia, rose to 420 metres above sea level, its original design level, for the first time since the power station began generating in 2022.
Nobody rushed it. The filling began on 25 September and climbed about 40 centimetres a day, stopping every three metres so engineers could check the dam, the works and the surrounding slopes, according to a statement from the utility EPM published by Medellín's city hall. It took 45 days to add 12 metres of water.
- What happened: the reservoir went from elevation 408 to 420, the maximum level in the original design.
- How much water: roughly 400 million additional cubic metres, equal to about 187 GWh of stored energy.
- What it is for: a reserve for the driest months of El Niño, which EPM expects between December and April.
- What is still missing: the plant's second stage, with four more turbines, is 96.47% complete.
Today Hidroituango reached elevation 420 metres above sea level, the original design level of its reservoir.
John Maya Salazar, general manager of EPM
Why would a three-digit number make the front pages of El Tiempo, Portafolio and El Colombiano? The answer lies in two calendars: the climate's and the project's own.
Twelve metres worth two weeks of power for Medellín
The clearest comparison came from the company itself. The 187 GWh now stored above the previous level would cover roughly 15 days of Medellín's electricity demand, in a city of more than two and a half million people. El Tiempo reported another EPM equivalence: the extra reserve delivers as much as a 130-megawatt thermal plant running without pause through the dry season.
Volume figures differ slightly between sources. EPM's official statement spoke of around 400 million cubic metres; local outlet Minuto30 reported close to 390 million. The gap is small and does not change the core fact: the reservoir, a body of water stretching more than 70 kilometres through the Cauca canyon, now holds more water than it ever has.

Why now
Colombia's weather agency, IDEAM, officially declared El Niño on 8 October. According to official information reported in the press, the event could remain strong to very strong until at least March 2027, with an 83% probability. For a country that makes most of its electricity from water, that means thinner rivers at exactly the moment heat pushes up the use of fans and air conditioning.
The grid operator, XM, has been running a countdown for weeks. In its bulletin for 6 to 12 November, reported by La República, national usable reservoir storage closed at 78.48%, barely half a point up on the previous week. River inflows in November stood at 54% of the historical average, and at 52% in Antioquia. The rainy season ends, according to XM, on 30 November.
Against that backdrop, Hidroituango's 12 metres do not solve the problem, but they widen the margin. Demand on Colombia's national grid is running 5.84% above 2025, according to the same XM bulletin, and EPM itself estimates a firm-energy shortfall of more than 2.5% in 2026 that could rise to 4.5% in 2027 unless new generation comes online.
The same bulletin offers another yardstick for the challenge. Compared with the dry season of 2015 and 2016, the last strong El Niño that forced national savings campaigns, the grid now has to meet about 68 GWh more demand every day. To protect reserves, a minimum daily thermal-generation requirement has been in force since 7 September, though XM found it was met on only 12 of the 67 days assessed, with an average of 87.10 GWh a day. Colombia's Energy and Gas Regulation Commission has also set a 30% floor for national reservoir storage, a threshold XM says could be reached by April 2027 unless thermal plants generate steadily above 85 GWh a day. Every cubic metre stored in Antioquia this November is one more piece in a national puzzle.
There is a regional contrast, too. While inflows in Antioquia and the country's centre were running at roughly half their usual level, the Caribbean region recorded 91% of its historical average in November, according to XM, although its weight in the national total is under 2%.
A climb watched by 3,600 sensors
Filling the reservoir higher than ever before was not decided overnight. EPM applied to Colombia's National Environmental Licensing Authority (ANLA) in April 2026, and the request was settled in stages: in May the company confirmed a first favourable communication, El Colombiano reported, and in September came the final go-ahead to start raising the level.
There was work to do on the slopes first. After the 2018 emergency, EPM had halted vegetation clearing along the reservoir's banks, and before flooding the new 12 metres that biomass had to be removed: about 68 hectares, according to the company, so that organic matter would not rot underwater and degrade water quality. The job included rescuing plants and relocating wildlife, with ANLA carrying out verification visits. The Environment Ministry put the cost of that clearing at about 36 billion pesos.
During the filling, a technical centre tracked more than 2,000 variables in real time, with daily working sessions on river flow, geotechnical behaviour and social and environmental issues, El Colombiano reported. The 225-metre dam carries more than 3,600 measuring instruments which, according to EPM, can pick up abnormal conditions up to 40 hours in advance.
We will have to save water, and we will have to save energy too.
Federico Gutiérrez, mayor of Medellín, on the day the reservoir hit its design level
What the works say: four turbines running, four on the way
Hidroituango is set to become Colombia's largest hydroelectric plant. Its main works lie in the municipalities of Ituango and Briceño, and twelve municipalities in northern and western Antioquia make up its area of influence. The project is owned by the Sociedad Hidroituango, whose manager is Carolina Escobar; EPM builds and operates it.
Four generating units of up to 300 megawatts each are running today, 1,200 MW in total. The first two entered commercial operation between September and October 2022; the third and fourth between October and November 2023. Together they supply between 11% and 12% of the energy Colombia consumes, according to figures given in November by the Mines and Energy Minister, María Nohemí Arboleda, and by the presidency.

The second stage
The machine hall, carved inside the mountain, is 240 metres long, 23 metres wide and 49 metres high. It was designed for eight Francis turbines. In units 5, 6 and 7 the stay rings and spiral cases, the parts that channel water towards the runner, are already in place; the next step is to assemble the rotor and stator of units 5 and 6.
Progress on that second stage stood at 96.47% as of 31 October, according to EPM, and about 4,800 people work on it. The official schedule has unit 5 starting in November 2027 and unit 6 in December 2027, with units 7 and 8 following in the first half of 2028.
Once all eight machines are running, the plant will reach 2,400 MW and could cover about 17% of the energy Colombia needs. Two units at full load are enough to meet Medellín's demand, according to EPM figures reported by El Tiempo.
A project with a difficult past
Elevation 420 carries extra weight because of what happened in 2018. On 28 April that year, landslides blocked the diversion tunnel while the dam was still unfinished. The reservoir began filling uncontrollably and, to stop water from overtopping the dam, engineers let it flow through the powerhouse. Downstream evacuations reached about 25,000 people, and the plant's start was pushed back by four years.
That emergency also left a long public, legal and social debate over the project, with riverside communities and organisations raising concerns for years about its effects on the Cauca canyon. EPM and Medellín's city hall, for their part, report a 2.5-trillion-peso social and environmental management plan that, by their own figures, includes roads, schools and housing in the surrounding municipalities.
On 9 November, officials at the reservoir included the Mines and Energy Minister, the Environment Minister, Fabio Arjona, ANLA's director, Sergio Piñeros, Antioquia's governor, Andrés Julián Rendón, and Medellín's mayor. Representatives of different levels of government agreed in calling the plant a strategic asset for the country.
This project is Antioquia's and the country's energy guarantee.
Andrés Julián Rendón, governor of Antioquia
What still needs to happen
The first task is to keep the reservoir high for as long as the rains last and then manage that saving carefully through the drought. EPM has stressed that monitoring of the dam and the slopes remains active, and the national government has asked households and businesses to cut consumption. Since the Voluntary Savings Programme began, regulated demand in November has fallen 4.37% compared with August, according to XM.
The second is to finish the four remaining turbines. A store of water is of limited use without machines to turn it into electricity in the years when the firm-energy shortfall could widen. That is why, for the sector, the 2027 and 2028 deadlines are the other half of this story.
Colombia is not the only country preparing for this El Niño with water in the bank. In Ecuador, farmers are better placed than in 1998, as we reported in El cacao rinde el doble: por qué el campo llega a este Niño mejor que en 1998, and the same country has just switched on its biggest solar farm, covered in 105.000 paneles en Santa Elena: arranca el mayor parque solar de Ecuador. Diversification is moving at a global scale too, as we explained in Arena, arcilla y óxido: las diez tecnologías energéticas que pueden escalar antes de 2030.
In Antioquia, public engineering delivered another recent piece of good news with La Universidad de Antioquia fabrica 1,7 millones de pastillas contra la malaria. And the slope monitoring that accompanied the filling echoes what Manizales has done for decades, told in Mil obras, 80 guardianas y cero muertes por deslizamientos en 2024.
The detail you may not know
The cavern where Hidroituango's four turbines now spin was flooded for 271 days after the 2018 emergency, El Tiempo recalled this week. It had to be drained, cleaned and rebuilt from the inside. The same rock walls the river once filled with mud now house the machines which, with the reservoir at elevation 420, have the largest store of water in their history behind them.
Further reading
- EPM's statement on elevation 420, in Medellín city hall's press room.
- XM electricity market bulletins, with weekly reservoir levels.
- IDEAM forecasts and alerts on El Niño.
- Ministry of Mines and Energy, with its energy-saving campaigns.
- Antioquia's departmental government, a partner in the project through the Sociedad Hidroituango.
Go further
- Web · EPM / Alcaldía de MedellínEl embalse de Hidroituango alcanzó la cota 420 y contribuirá a afrontar el período más retador de El Niño
El comunicado oficial con las cifras del llenado y del avance de la segunda etapa.
- Web · Alcaldía de Medellín¿Qué es Hidroituango y cómo lo reconstruimos?
Una línea de tiempo oficial desde la contingencia de 2018 hasta el encendido de las turbinas.
- Web · El ColombianoCómo llegó el embalse de Hidroituango a la cota 420
Reconstruye los 45 días de llenado y el sistema de vigilancia en tiempo real.
- Web · La RepúblicaXM advierte que quedan 16 días para llenar los embalses antes del verano con El Niño
El estado de las reservas de todo el país, semana a semana.
- Web · Hidroituango S.A. E.S.P.Sociedad Hidroituango
La web de la propietaria del proyecto, con comunicados y datos técnicos.
- Blog · Mongabay LatamColombia: el territorio indígena que ahogó la poderosa Hidroituango
Otra mirada: un reportaje sobre las comunidades del cañón afectadas por el embalse.
Sources
- El embalse de Hidroituango alcanzó la cota 420 (EPM, Alcaldía de Medellín)
- Hidroituango alcanza su nivel máximo y se prepara para el fenómeno de El Niño (Portafolio)
- Hidroituango alcanza la cota 420 (El Tiempo)
- En las entrañas de Hidroituango (El Tiempo)
- Cómo llegó el embalse de Hidroituango a la cota 420 (El Colombiano)
- Hidroituango alcanzó la cota 420 (Minuto30)
- XM advierte que quedan 16 días para llenar los embalses (La República)
- Hidroituango podrá subir a su nivel máximo para enfrentar El Niño (Hoy Diario del Magdalena)
- EPM confirmó vía libre para subir embalse de Hidroituango (El Colombiano)