Walking and thinking: what philosophers sensed and a study of 3,093 adults begins to measureFrom Quito's Polytechnic to Rome: an Ecuadorian physicist studies the first galaxies with WebbFrom 14 to 52 donors per million: what changed in Spain's hospitals after 1989Ecuador wins its eighth Pan American German Shepherd breeding title in LimaJefferson, Seneca and the old question behind open scienceCicero called gratitude the mother of virtues. Buffett wants you to try it this week38 patients from 12 provinces got their hearing implants and devices in CuencaQuito physicist wins prize to map in 3D how the liver repairs itselfDaily iron for children: 114 studies, one clear benefit and several caveatsThe bear cave nobody will enter again, and what is gained by sealing itWalking and thinking: what philosophers sensed and a study of 3,093 adults begins to measureFrom Quito's Polytechnic to Rome: an Ecuadorian physicist studies the first galaxies with WebbFrom 14 to 52 donors per million: what changed in Spain's hospitals after 1989Ecuador wins its eighth Pan American German Shepherd breeding title in LimaJefferson, Seneca and the old question behind open scienceCicero called gratitude the mother of virtues. Buffett wants you to try it this week38 patients from 12 provinces got their hearing implants and devices in CuencaQuito physicist wins prize to map in 3D how the liver repairs itselfDaily iron for children: 114 studies, one clear benefit and several caveatsThe bear cave nobody will enter again, and what is gained by sealing it

Twelve more metres of water before El Niño: Hidroituango finally hits its design level

The reservoir of the Antioquia power plant reached elevation 420, its original design level, on 9 November, storing about 187 GWh of extra energy for the driest months of El Niño.

File photo: aerial view of the Hidroituango dam and reservoir in Antioquia, Colombia, in 2022.
File photo: aerial view of the Hidroituango dam and reservoir in Antioquia, Colombia, in 2022. Photo: Presidencia de la República de Colombia / Wikimedia Commons, CC0

On Monday 9 November, the Cauca River reached a line engineers had drawn on their plans more than a decade ago. The reservoir behind Hidroituango, in northern Antioquia, rose to 420 metres above sea level, its original design level, for the first time since the power station began generating in 2022.

Nobody rushed it. The filling began on 25 September and climbed about 40 centimetres a day, stopping every three metres so engineers could check the dam, the works and the surrounding slopes, according to a statement from the utility EPM published by Medellín's city hall. It took 45 days to add 12 metres of water.

  • What happened: the reservoir went from elevation 408 to 420, the maximum level in the original design.
  • How much water: roughly 400 million additional cubic metres, equal to about 187 GWh of stored energy.
  • What it is for: a reserve for the driest months of El Niño, which EPM expects between December and April.
  • What is still missing: the plant's second stage, with four more turbines, is 96.47% complete.

Today Hidroituango reached elevation 420 metres above sea level, the original design level of its reservoir.

John Maya Salazar, general manager of EPM

Why would a three-digit number make the front pages of El Tiempo, Portafolio and El Colombiano? The answer lies in two calendars: the climate's and the project's own.

Twelve metres worth two weeks of power for Medellín

The clearest comparison came from the company itself. The 187 GWh now stored above the previous level would cover roughly 15 days of Medellín's electricity demand, in a city of more than two and a half million people. El Tiempo reported another EPM equivalence: the extra reserve delivers as much as a 130-megawatt thermal plant running without pause through the dry season.

Volume figures differ slightly between sources. EPM's official statement spoke of around 400 million cubic metres; local outlet Minuto30 reported close to 390 million. The gap is small and does not change the core fact: the reservoir, a body of water stretching more than 70 kilometres through the Cauca canyon, now holds more water than it ever has.

File photo: the Cauca River canyon in the Hidroituango area, before the reservoir was filled.
File photo: the Cauca River canyon in the Hidroituango area, before the reservoir was filled. · Hidroituango / Wikimedia Commons, CC BY 2.0

Why now

Colombia's weather agency, IDEAM, officially declared El Niño on 8 October. According to official information reported in the press, the event could remain strong to very strong until at least March 2027, with an 83% probability. For a country that makes most of its electricity from water, that means thinner rivers at exactly the moment heat pushes up the use of fans and air conditioning.

The grid operator, XM, has been running a countdown for weeks. In its bulletin for 6 to 12 November, reported by La República, national usable reservoir storage closed at 78.48%, barely half a point up on the previous week. River inflows in November stood at 54% of the historical average, and at 52% in Antioquia. The rainy season ends, according to XM, on 30 November.

Against that backdrop, Hidroituango's 12 metres do not solve the problem, but they widen the margin. Demand on Colombia's national grid is running 5.84% above 2025, according to the same XM bulletin, and EPM itself estimates a firm-energy shortfall of more than 2.5% in 2026 that could rise to 4.5% in 2027 unless new generation comes online.

The same bulletin offers another yardstick for the challenge. Compared with the dry season of 2015 and 2016, the last strong El Niño that forced national savings campaigns, the grid now has to meet about 68 GWh more demand every day. To protect reserves, a minimum daily thermal-generation requirement has been in force since 7 September, though XM found it was met on only 12 of the 67 days assessed, with an average of 87.10 GWh a day. Colombia's Energy and Gas Regulation Commission has also set a 30% floor for national reservoir storage, a threshold XM says could be reached by April 2027 unless thermal plants generate steadily above 85 GWh a day. Every cubic metre stored in Antioquia this November is one more piece in a national puzzle.

There is a regional contrast, too. While inflows in Antioquia and the country's centre were running at roughly half their usual level, the Caribbean region recorded 91% of its historical average in November, according to XM, although its weight in the national total is under 2%.

A climb watched by 3,600 sensors

Filling the reservoir higher than ever before was not decided overnight. EPM applied to Colombia's National Environmental Licensing Authority (ANLA) in April 2026, and the request was settled in stages: in May the company confirmed a first favourable communication, El Colombiano reported, and in September came the final go-ahead to start raising the level.

There was work to do on the slopes first. After the 2018 emergency, EPM had halted vegetation clearing along the reservoir's banks, and before flooding the new 12 metres that biomass had to be removed: about 68 hectares, according to the company, so that organic matter would not rot underwater and degrade water quality. The job included rescuing plants and relocating wildlife, with ANLA carrying out verification visits. The Environment Ministry put the cost of that clearing at about 36 billion pesos.

During the filling, a technical centre tracked more than 2,000 variables in real time, with daily working sessions on river flow, geotechnical behaviour and social and environmental issues, El Colombiano reported. The 225-metre dam carries more than 3,600 measuring instruments which, according to EPM, can pick up abnormal conditions up to 40 hours in advance.

We will have to save water, and we will have to save energy too.

Federico Gutiérrez, mayor of Medellín, on the day the reservoir hit its design level

What the works say: four turbines running, four on the way

Hidroituango is set to become Colombia's largest hydroelectric plant. Its main works lie in the municipalities of Ituango and Briceño, and twelve municipalities in northern and western Antioquia make up its area of influence. The project is owned by the Sociedad Hidroituango, whose manager is Carolina Escobar; EPM builds and operates it.

Four generating units of up to 300 megawatts each are running today, 1,200 MW in total. The first two entered commercial operation between September and October 2022; the third and fourth between October and November 2023. Together they supply between 11% and 12% of the energy Colombia consumes, according to figures given in November by the Mines and Energy Minister, María Nohemí Arboleda, and by the presidency.

File photo: heavy machinery at work on the Hidroituango dam during construction.
File photo: heavy machinery at work on the Hidroituango dam during construction. · Algorithmix / Wikimedia Commons, CC0

The second stage

The machine hall, carved inside the mountain, is 240 metres long, 23 metres wide and 49 metres high. It was designed for eight Francis turbines. In units 5, 6 and 7 the stay rings and spiral cases, the parts that channel water towards the runner, are already in place; the next step is to assemble the rotor and stator of units 5 and 6.

Progress on that second stage stood at 96.47% as of 31 October, according to EPM, and about 4,800 people work on it. The official schedule has unit 5 starting in November 2027 and unit 6 in December 2027, with units 7 and 8 following in the first half of 2028.

Once all eight machines are running, the plant will reach 2,400 MW and could cover about 17% of the energy Colombia needs. Two units at full load are enough to meet Medellín's demand, according to EPM figures reported by El Tiempo.

A project with a difficult past

Elevation 420 carries extra weight because of what happened in 2018. On 28 April that year, landslides blocked the diversion tunnel while the dam was still unfinished. The reservoir began filling uncontrollably and, to stop water from overtopping the dam, engineers let it flow through the powerhouse. Downstream evacuations reached about 25,000 people, and the plant's start was pushed back by four years.

That emergency also left a long public, legal and social debate over the project, with riverside communities and organisations raising concerns for years about its effects on the Cauca canyon. EPM and Medellín's city hall, for their part, report a 2.5-trillion-peso social and environmental management plan that, by their own figures, includes roads, schools and housing in the surrounding municipalities.

On 9 November, officials at the reservoir included the Mines and Energy Minister, the Environment Minister, Fabio Arjona, ANLA's director, Sergio Piñeros, Antioquia's governor, Andrés Julián Rendón, and Medellín's mayor. Representatives of different levels of government agreed in calling the plant a strategic asset for the country.

This project is Antioquia's and the country's energy guarantee.

Andrés Julián Rendón, governor of Antioquia

What still needs to happen

The first task is to keep the reservoir high for as long as the rains last and then manage that saving carefully through the drought. EPM has stressed that monitoring of the dam and the slopes remains active, and the national government has asked households and businesses to cut consumption. Since the Voluntary Savings Programme began, regulated demand in November has fallen 4.37% compared with August, according to XM.

The second is to finish the four remaining turbines. A store of water is of limited use without machines to turn it into electricity in the years when the firm-energy shortfall could widen. That is why, for the sector, the 2027 and 2028 deadlines are the other half of this story.

Colombia is not the only country preparing for this El Niño with water in the bank. In Ecuador, farmers are better placed than in 1998, as we reported in El cacao rinde el doble: por qué el campo llega a este Niño mejor que en 1998, and the same country has just switched on its biggest solar farm, covered in 105.000 paneles en Santa Elena: arranca el mayor parque solar de Ecuador. Diversification is moving at a global scale too, as we explained in Arena, arcilla y óxido: las diez tecnologías energéticas que pueden escalar antes de 2030.

In Antioquia, public engineering delivered another recent piece of good news with La Universidad de Antioquia fabrica 1,7 millones de pastillas contra la malaria. And the slope monitoring that accompanied the filling echoes what Manizales has done for decades, told in Mil obras, 80 guardianas y cero muertes por deslizamientos en 2024.

The detail you may not know

The cavern where Hidroituango's four turbines now spin was flooded for 271 days after the 2018 emergency, El Tiempo recalled this week. It had to be drained, cleaned and rebuilt from the inside. The same rock walls the river once filled with mud now house the machines which, with the reservoir at elevation 420, have the largest store of water in their history behind them.

Further reading

Go further

How did this make you feel?

Get only good news

Every morning, the best stories of the day in your inbox. Free, no noise, unsubscribe in one click.

Free until 1 June 2027. We only use your email for the newsletter and never share it.

Keep reading

National · Chocó

Three months after the quake, El Dos begins building its first 92 homes

In the Chocó village of El Dos, Adopta un Hogar laid the first stone of 92 earthquake-resistant homes for affected families. In Quibdó, work begins on the city's first recycling station, built for the 60 waste pickers at the Marmolejo landfill.

National · Risaralda

Risaralda has 555 home improvements under way, and Pereira has finished 63 of 150

Colombia's Housing Ministry says its agreement with the Risaralda government covers 555 home improvements in Pereira, Dosquebradas, La Virginia and Santa Rosa de Cabal. Pereira has already handed over 63.

Economy · Yucatán

Yucatán grows 4.3% and its industry 7.8% while Campeche and Quintana Roo shrink

According to INEGI, Yucatán was the only state on the peninsula to grow year on year in the second quarter of 2026: 4.3% overall and 7.8% in industry.

Economy · Región de Murcia

Murcia's exports climb 9% and an easy-open olive jar takes gold in London

Murcian sales abroad grew 9% between January and August. In London, Sonoco and Olispania, an olive company from Jumilla, shared a gold award for a jar lid that needs half the force to open.

The news, calmly · Colombia

The OECD puts numbers on Colombia's fiscal challenge: what its new report says

OECD Secretary-General Mathias Cormann presented the Economic Survey of Colombia 2026 in Bogotá this Friday: a 7.2% of GDP deficit, inflation above target, and a roadmap of reforms for the years ahead.

The news, calmly · Colombia

Colombia's dollar jumped 88 pesos in a day, yet is still cheaper than in January

Friday's official exchange rate is 3,415.10 pesos per dollar after the sharpest rise in months. What drove it, who it hurts, who it helps, and why it is worth keeping in perspective.

From other sections

Wellbeing · International

Daily iron for children: 114 studies, one clear benefit and several caveats

A Cochrane review published on 16 November pools 114 trials with 50,325 children. Daily iron reduces iron deficiency anaemia without more common infections, and the authors ask for local anaemia rates to guide decisions.

Ideas · International

The bear cave nobody will enter again, and what is gained by sealing it

A mountain guide found a cavity full of ancient bear bones in the Dolomites and reported it to the authorities, who sealed it. Plato, Aristotle and the psychology of awe help explain what someone gains by not keeping a discovery to themselves.

The news, calmly · Colombia

The OECD puts numbers on Colombia's fiscal challenge: what its new report says

OECD Secretary-General Mathias Cormann presented the Economic Survey of Colombia 2026 in Bogotá this Friday: a 7.2% of GDP deficit, inflation above target, and a roadmap of reforms for the years ahead.

The news, calmly · Colombia

Colombia's dollar jumped 88 pesos in a day, yet is still cheaper than in January

Friday's official exchange rate is 3,415.10 pesos per dollar after the sharpest rise in months. What drove it, who it hurts, who it helps, and why it is worth keeping in perspective.

Laws & agreements · International

Three months, not nine years: the EU fast-tracks clean-energy paperwork

The European Parliament and the Council agreed in the early hours of November 18 to cap permitting times for solar panels, batteries and EV chargers at a few months, down from processes that can today drag on for nearly a decade.

Technology · International

Electric trucks now make up half of China's heavy-truck sales

In September, for the first time, more than half the heavy trucks sold in China were electric, driven by a growing network of battery-swap stations that can already replace a full battery pack in five minutes.

Welcome to The Positive Way

Start your day with what's going right: progress, ideas worth thinking about and people who inspire. Because the world moves forward every day, and that deserves to be told.

Get only good news

Every morning, the best stories of the day in your inbox. Free, no noise, unsubscribe in one click.

Free until 1 June 2027. We only use your email for the newsletter and never share it.