A year of ferries ends: Lansing's new Mississippi bridge opens five months early
The $165 million crossing between northeast Iowa and southwest Wisconsin opened to traffic on Nov. 6, replacing the 1931 Black Hawk Bridge that was blown up last December. It was not due until spring 2027.

Curtis Snitker remembers walking across the old bridge in Lansing, Iowa, and looking down through the deck. "It was just wood," he told KTTC on the morning of Nov. 6, 2026, as he waited with his neighbors for the ribbon to be cut on its replacement.
Around noon, the first cars rolled onto a steel truss that looks almost exactly like the one the town lost. The difference is underneath: foundations driven 150 feet into bedrock, lanes wide enough for a combine, and a schedule that beat the original target by five months.
For a year, the only way across the Mississippi here had been a free car ferry or a long drive south. Now the river towns of Allamakee County, Iowa, and Crawford County, Wisconsin, are joined again.
- What opened: the Iowa 9 / Wisconsin 82 bridge at Lansing, a $165 million steel truss across the Mississippi.
- When: Friday, Nov. 6, 2026, about five months ahead of the spring 2027 target.
- Who paid: about $112 million came from federal sources; Iowa and Wisconsin split the rest.
- Why it matters: it is the only crossing on a roughly 60-mile stretch of the river between La Crosse and Prairie du Chien.
The bridge that sang
The Black Hawk Bridge opened on June 17, 1931. It was built as a private toll crossing by the Iowa-Wisconsin Bridge Company, designed by engineer Melvin B. Stone, with trusses erected by the McClintic-Marshall Company of Chicago. At 1,653 feet long, with a main span of 653 feet, it was a riveted cantilever through truss, an unusual design among Mississippi River bridges. Locals simply called it the Lansing bridge.
Its open grate deck hummed under tires. People in Lansing said the bridge sang.
Its life was never easy. Ice jams damaged it badly enough that it was closed from 1945 to 1957; the toll company could not pay for repairs and went out of business, and the two states bought and fixed it. Cracks and shifting piers brought new closures in 2011, 2024 and 2025. By the end, federal inspectors gave it a sufficiency rating of 39.9 percent, mostly because it was simply obsolete: two lanes, 21 feet wide, built for the cars of the Hoover years.

The Iowa Department of Transportation started feasibility studies for a replacement in 2004. Construction finally began in September 2023, with the plan of keeping the old bridge open until the new one was ready.
The river had other plans. Problems with the old foundations during construction destabilized the 1931 structure, and on Oct. 20, 2025, it closed for good. On Dec. 19, 2025, crews brought down its central span with explosives and it dropped into the Mississippi.
A year on the water
Losing the bridge cut a rural region in half. Farmers, commuters, students and shop owners who crossed daily suddenly faced a detour through Marquette, Iowa, and Prairie du Chien, Wisconsin, about 30 miles downriver.
The two transportation departments responded with a free car ferry, which started running on Nov. 3, 2025, operated by two different companies and paid for jointly by Iowa and Wisconsin. By the end of August 2026 it had carried almost 131,000 vehicles. By the day the bridge opened, the total had passed 160,000.
That number explains the crowd on opening day. Sherry Quamme, who lives on a bluff near Ferryville, Wisconsin, and chairs the Wisconsin side of the Mississippi River Parkway Commission, had watched three years of construction from her window. She told Wisconsin Public Radio that about 2,300 cars a day crossed the old bridge in 2024.
The Black Hawk Bridge is the artery that moves the traffic as lifeblood to the entire region.
Sherry Quamme, Wisconsin chair, Mississippi River Parkway Commission
Wisconsin Gov. Tony Evers, who attended the ribbon cutting, did not pretend the year had been easy. "We know that closure created real hardships," he said, according to WPR.
Building it twice as deep, and faster
The new crossing was designed to look like the old one because residents asked for it. From a distance it has the same skeletal profile of white steel over brown water. Up close, almost everything is different.
The deck is about 40 feet wide, close to double the 21 feet of 1931, with real shoulders so trucks and farm machinery can pass each other. The central span is wider to give barges more room in the navigation channel, and the intersection on the Iowa side was enlarged for big vehicles.
The foundations reach 150 feet into bedrock, nearly three times deeper than the original, according to the Iowa DOT. The old bridge's foundations were the reason it failed earlier than expected.
Crews poured about 11,400 cubic yards of concrete and used 6,600 tons of steel. Iowa DOT Director Scott Marler put the steel in perspective at the ceremony: "That's pretty close to the amount of steel in the Eiffel Tower."

How did a project of that size finish five months early? Project manager Clayton Burke told Iowa Public Radio that crews worked "as fast as they possibly could," on 10-hour shifts, seven days a week. More than 60 contractors, consultants and industry partners took part, according to the state. When the early date was announced in September, Iowa Gov. Kim Reynolds singled out Kraemer North America among the builders and called the bridge "a wonderful gift, and just in time for the holiday season and winter travel."
Burke described a project "supported by so many excellent people, groups, teams, communities, and states."
What the numbers say
The bridge is expected to carry about 2,500 vehicles a day, slightly more than the old crossing handled before it closed. The total cost was $165 million, with roughly $112 million in federal money and the remainder shared by the two states, according to Iowa Public Radio and WPR.
That money buys more than convenience. On this stretch of the Upper Mississippi, the river is a hard border: the next bridges are at La Crosse to the north and Prairie du Chien to the south. A tavern in De Soto, a grain elevator in Allamakee County and a clinic appointment across the river all depend on the same span of steel.
Lansing resident Snitker summed it up for KTTC: "Now, that old bridge is gone. We have this new beautiful bridge. It opens up commerce for both sides of the river."

David Koziol of Lynxville, Wisconsin, was first in line on the Wisconsin side. He remembered driving over the old bridge in the 1980s and called it "a very iconic bridge." He got to be among the first on the new one.
The town of Lansing also made the day its own. Main Street Lansing, the local downtown group, sponsored the procession across the bridge, sold raffle tickets for a chance to be in one of the first cars, and is raising $170,000 to light the bridge's south side.
A road with a river attached
The bridge is also a link in a much longer chain. Both banks here belong to the Great River Road, the scenic route that follows the Mississippi for nearly 3,000 miles through 10 states, according to the Mississippi River Parkway Commission. Quamme, who chairs the commission's Wisconsin side, sees the crossing as part of that larger network: a place where visitors drawn by bluffs, eagles and river towns can loop from one state to the other instead of turning back.
That matters for small places like Lansing, Ferryville, De Soto and Lynxville, where a weekend of visitors can make a month for a café or an antique shop. Evers used his remarks at the ceremony to thank the project teams and to stress the bridge's importance for regional tourism and economic growth, according to the Iowa DOT.
The year without a bridge also taught the region something about itself. The ferry, a stopgap that nobody wanted, carried an average of more than 400 vehicles a day across the river, and people kept coming back to it. Commuters learned the schedule, school buses and delivery vans planned around it, and the two states kept it free.
Timeline of a crossing:
- June 17, 1931: the privately built Black Hawk Bridge opens as a toll crossing.
- 1945-1957: ice-jam damage closes it; Iowa and Wisconsin take it over and repair it.
- 2004: Iowa DOT begins studying a replacement.
- September 2023: construction of the new bridge starts.
- Oct. 20, 2025: the old bridge closes for good.
- Nov. 3, 2025: the free car ferry begins.
- Dec. 19, 2025: the 1931 span is demolished with explosives.
- Nov. 6, 2026: the new bridge opens, five months early.
What is still to do
The ribbon is cut, but the job is not over. The Iowa DOT says crews still have to restore the ferry landings on both banks and pull the old piers and foundations out of the river. Deck work in spring 2027 will slow traffic at times, but the agency expects no full closures. The whole project should be complete by late spring 2027.
The ferry, meanwhile, made its last trips at the end of the day on Nov. 6.
This is one of several stories of rural America putting infrastructure back to work that The Positive Way has followed this autumn, from Colorado's optional parks pass that raised $43.2 million to Pennsylvania volunteers who turned borrowed fields into 80,000 pounds of free food. Further north, sockeye salmon returning to the upper Columbia show what happens when a river crossing is designed with the river in mind.
The detail you might not know
The old Black Hawk Bridge was born as a business. For its first two decades, drivers paid a private company to cross. It was the 1945 ice jam, and the company's inability to pay for repairs, that turned it into a public road. Eighty years later, the replacement was funded mostly by Washington, built by two states, designed to look like the original at the request of the people who live under it, and opened in time for Thanksgiving traffic.
Further reading
Go further
- Web · Iowa DOTIowa and Wisconsin leaders celebrate opening of the Lansing bridge
The official account of the opening, with the engineering figures straight from the people who built it.
- Web · Wisconsin Public RadioNew Mississippi River bridge opens in southwest Wisconsin
The view from the Wisconsin bluffs, where the crossing is the only one for about 60 miles.
- Web · Iowa Public RadioA much-awaited Mississippi River bridge is open in northeast Iowa
Good on the design choices that make the new truss look like the 1931 original.
- Web · WikipediaBlack Hawk Bridge
The long history of the old cantilever bridge, from private toll crossing to demolition.
- Web · Wisconsin DOTNew WIS 82 / IA 9 Mississippi River Bridge anticipated to open in early November
How the two states coordinated the opening date across the river.
- Web · MPR NewsNew Mississippi River Lansing bridge linking Iowa, Wisconsin set to open
A preview written in the days before the ribbon was cut.
Sources
- Iowa DOT: Iowa and Wisconsin leaders celebrate opening of Iowa 9/WIS 82 Mississippi River bridge at Lansing
- Iowa Public Radio: A much-awaited Mississippi River bridge is open in northeast Iowa
- KTTC: New $165M Lansing bridge opens 5 months early
- WPR: New Mississippi River bridge opens in southwest Wisconsin
- Iowa DOT: early November opening announced