Walking and thinking: what philosophers sensed and a study of 3,093 adults begins to measureFrom Quito's Polytechnic to Rome: an Ecuadorian physicist studies the first galaxies with WebbFrom 14 to 52 donors per million: what changed in Spain's hospitals after 1989Ecuador wins its eighth Pan American German Shepherd breeding title in LimaJefferson, Seneca and the old question behind open scienceCicero called gratitude the mother of virtues. Buffett wants you to try it this week38 patients from 12 provinces got their hearing implants and devices in CuencaQuito physicist wins prize to map in 3D how the liver repairs itselfDaily iron for children: 114 studies, one clear benefit and several caveatsThe bear cave nobody will enter again, and what is gained by sealing itWalking and thinking: what philosophers sensed and a study of 3,093 adults begins to measureFrom Quito's Polytechnic to Rome: an Ecuadorian physicist studies the first galaxies with WebbFrom 14 to 52 donors per million: what changed in Spain's hospitals after 1989Ecuador wins its eighth Pan American German Shepherd breeding title in LimaJefferson, Seneca and the old question behind open scienceCicero called gratitude the mother of virtues. Buffett wants you to try it this week38 patients from 12 provinces got their hearing implants and devices in CuencaQuito physicist wins prize to map in 3D how the liver repairs itselfDaily iron for children: 114 studies, one clear benefit and several caveatsThe bear cave nobody will enter again, and what is gained by sealing it

75-metre blades head for Loja as Ecuador's biggest wind farm passes 60%

Villonaco III, with 19 turbines and 112.1 megawatts on Huayrapamba hill, is more than 60% complete and in its final phase, Ecuador's energy minister said on 13 November. The roughly $230 million build is entirely privately funded.

File photo: Villonaco hill and the Loja valley. The new wind farm is being built on Huayrapamba hill, in the same range.
File photo: Villonaco hill and the Loja valley. The new wind farm is being built on Huayrapamba hill, in the same range. Photo: calu_777 / Wikimedia Commons, CC BY-SA 3.0

Ecuador's environment and energy minister, Juan Carlos Blum, was touring a fuel terminal in Guayaquil on Thursday 13 November when he gave the latest number for a project rising almost 600 kilometres away. The Villonaco III wind farm, in the southern province of Loja, is now more than 60% complete overall and has entered its final phase, El Universo reported.

The hardest pieces have already crossed the ocean. All 57 blades, each about 75 metres long, and the generators were unloaded at Puerto Bolívar, in El Oro province, and are moving by road towards Huayrapamba hill, between the cantons of Loja and Catamayo. Nineteen turbines will go up there, adding up to 112.1 megawatts: seven times the capacity of the wind farm Loja opened more than a decade ago on the neighbouring ridge.

  • Location: Huayrapamba hill, Chuquiribamba parish, at roughly 3,000 metres above sea level.
  • Capacity: 19 turbines of 5.9 MW each, 112.1 MW in total, the largest wind farm built in the country.
  • Money: about $230 million, all of it private capital, under a 25-year concession.
  • Progress: 63.90% of physical works in October 2026, according to the ministry, and more than 60% overall according to the minister.
  • Schedule: technical tests before October 2027 and commercial operation during 2027.

The minister said the plant's output could cover demand comparable to that of cities such as Durán and Milagro. That matters in a country that saw power cuts in Quito, Guayaquil and other cities again in October, during the dry season, when the rivers that drive the big hydroelectric dams run low.

Blum kept returning to one point: the source. "It is an important project," he said, adding that wind does not depend on rain or sunshine and that a grid fed by different sources spreads its risk better. Ecuador makes most of its electricity from water, so every megawatt that comes from elsewhere makes the system a little less exposed to drought.

Nineteen towers at 3,000 metres

The most visible part of the job is also the most delicate. Each blade is roughly as long as a 25-storey building laid on its side, and it has to travel from the coast to an Andean summit on roads built for buses and ordinary lorries.

The most complicated part of the project is the blades.

Juan Carlos Blum, Minister of Environment and Energy

He said so in early September, as the second shipment was due. The first, with 30 blades, docked at Puerto Bolívar at the end of August; the second, carrying the remaining 27, was expected on 16 September. Blum estimated at the time that moving them to the site would take about four months and called it the project's critical task, because of road capacity, bridges and the sheer size of the parts. Before the first blade left the port, the company ran transport simulations along the route, according to an August bulletin from the Ministry of Environment and Energy.

On the mountain, the ground came before the sky. A report in Loja's Periódico Independiente described road upgrades, earthworks, crane platforms and foundations in August. Access tracks were widened to six or seven metres, and the company opened a bypass so heavy machinery would not rumble through the village centre of Chuquiribamba.

Living next to a building site of this size has its costs, and the company says it keeps open channels with nearby communities to deal with complaints about dust and traffic. While the work lasts, tourist access to the area where the turbines are going up is restricted, so the hikers and families who usually climb the ridges around Loja on weekends will have to wait for the towers to be finished before they can get close.

The same report carried a figure people in the parish can feel: more than 700 direct jobs created during construction, with over 60% of the unskilled workforce drawn from Chuquiribamba and neighbouring Chantaco. The contract sets targets of 60% local workers and 50% local suppliers, and requires 12% of profits to be reinvested in the immediate area once the plant starts selling power.

File photo: a wind turbine blade on the road in Scotland. The Villonaco III blades are about 75 metres long and are travelling from Puerto Bolívar to Loja.
File photo: a wind turbine blade on the road in Scotland. The Villonaco III blades are about 75 metres long and are travelling from Puerto Bolívar to Loja. · Andrew Tryon / Wikimedia Commons, CC BY-SA 2.0

A weather mast on the hill has recorded average wind speeds of around 12 metres per second. On that basis the developer expects to generate about 360 gigawatt-hours a year, delivered to the Loja substation and into the national grid. The ministry puts the expected capacity factor at 37.4%, meaning the farm should on average produce a little over a third of what it would if it spun at full power every hour of the year.

Its older neighbour helps put that in perspective. The first Villonaco farm delivered 778.71 gigawatt-hours in almost eleven years, an average of roughly 71 gigawatt-hours a year. If the new plant meets its projections, it will produce about five times that every year.

The electricity will be sold to state distribution companies under long-term contracts at a tariff of 8.49 US cents per kilowatt-hour, Primicias reported in October.

What the first Villonaco taught

To see why a company would haul 19 turbines up a ridge in Loja, look at the hill next door. On Villonaco, about 14 kilometres from the city and some 2,720 metres up, eleven 1.5 MW turbines have been turning since 2013, for 16.5 MW in all. They are run by the state utility CELEC.

Construction started in June 2011 and finished in January 2013, and the farm began commercial operation on 1 July that year. By May 2024 it had fed 778.71 gigawatt-hours into the grid, enough for about 21,849 homes each month, according to figures published by El Oriente on its eleventh anniversary. More than 233,000 visitors have walked up to its viewpoint.

That performance earned it recognition in 2016 from the Chinese embassy and the turbine maker, Goldwind, as the highest capacity factor of any wind farm in the world, the trade magazine Energías Renovables reported. In August 2019 the farm broke its own monthly record, delivering 11,486 megawatt-hours with a capacity factor of 95.22% for the month. Around 4,300 people visited that same August.

The small farm also became a subject of study. The repository of the Universidad Politécnica Salesiana, for instance, holds a thesis devoted to evaluating its operating parameters.

The gap between the two generations shows in every machine. A turbine on the first Villonaco is rated at 1.5 MW; each new one is rated at 5.9 MW, almost four times as much. A turbine's output grows with the area its blades sweep, which is why manufacturers have moved in a decade from mid-sized rotors to 75-metre blades. Fewer towers produce more energy, and every foundation, access road and crane hour goes further.

File photo: working wind turbines and blades awaiting assembly beside a motorway in Germany.
File photo: working wind turbines and blades awaiting assembly beside a motorway in Germany. · Bärbel Miemietz / Wikimedia Commons, CC BY-SA 4.0

Loja is not alone in betting on wind. In Saraguro, on the border with Azuay province, the public company Elecaustro built the Minas de Huascachaca farm, with 50 MW and 14 turbines. Villonaco III will have more than twice that capacity.

The third phase took a long road. By 2019 it already appeared in government plans to attract private investment, and in December 2020 it was announced that the Spanish group Cobra would take it on. The concession contract was signed in July 2023, and an addendum in January 2025 got things moving: the concession has been in force since 15 January 2025 and construction began on 7 July that year. Former deputy minister Fernando Santos told Primicias that a trust had to be set up to guarantee payment for the electricity, tariffs had to be adjusted, and funds from the Inter-American Development Bank helped settle the matter.

Who is paying, and what is left

Villonaco III is the first generation project awarded through Ecuador's Public Selection Process to move ahead with international project finance. In plain terms, the banks lend against the farm's own future revenue, not against state guarantees.

Three development lenders are behind it. IDB Invest, the private-sector arm of the IDB Group, approved a $100 million loan to the project company Villonacoenergy on 8 September 2026 and rated it environmental category B, the band for impacts confined to the site and manageable with known measures. The Dutch development bank FMO and the French agency Proparco complete the package.

There is still work to do. The remaining components have to be hauled up the hill; the towers, nacelles and rotors assembled; the substation and the transmission line to Loja's substation finished; and the farm tested and connected to the national grid. The official timetable points to commercial operation in 2027: the ministry had pencilled in the third quarter, while the minister mentioned October 2027 in his latest update.

Blum also placed the project in a wider pipeline, saying some 3,000 megawatts of short-term private projects are waiting in the wings, mostly hydro plants of between 20 and nearly 100 megawatts. Since 12 November, Ecuador has also removed VAT on 104 kinds of equipment for solar, wind, hydro and storage plants, and on 5 November the country's largest solar park, at 82 peak megawatts, began operating in Santa Elena. Villonaco III is the wind piece of the same shift.

It is also something of an exception. According to Santos, it is the only large privately run non-conventional renewable project that has genuinely advanced. El Aromo, a 200 MW solar plant awarded in Manabí in 2020, shows no known progress, and the 45 MW Yanahurco wind project is not yet running. The Loja farm getting from paperwork to cranes is a test case for those coming after it.

The trend reaches well beyond Ecuador. Solar and wind equipment already accounts for $1.8 trillion in exports a year worldwide, and former oil yards such as Nigg in Scotland now build parts for the wind industry.

In Loja the change will be measured closer to home. The province, which has just seen Podocarpus National Park grow by 15,108 hectares, will soon see 19 towers on the Huayrapamba skyline, turning in the same wind that a decade ago made a small hill a world record holder.

File photo: the City Gate in central Loja, capital of the province where Villonaco III is being built.
File photo: the City Gate in central Loja, capital of the province where Villonaco III is being built. · Arabsalam / Wikimedia Commons, CC BY-SA 4.0

Further reading

Go further

How did this make you feel?

Get only good news

Every morning, the best stories of the day in your inbox. Free, no noise, unsubscribe in one click.

Free until 1 June 2027. We only use your email for the newsletter and never share it.

Keep reading

People · Ecuador

From Quito's Polytechnic to Rome: an Ecuadorian physicist studies the first galaxies with Webb

Mario Llerena graduated in physics from Escuela Politécnica Nacional in 2016 and now researches at the Rome Observatory, where he has won two INAF grants worth 31,000 euros in total.

Sports · Ecuador

Ecuador wins its eighth Pan American German Shepherd breeding title in Lima

Two Ecuadorian females won their classes at the COAPA Peru 2026 championship, and the delegation placed nine dogs among the best in their categories. Here is how a title that rewards a whole country, not a single dog, is scored.

Science and health · Azuay

38 patients from 12 provinces got their hearing implants and devices in Cuenca

The Vicente Corral Moscoso Hospital in Cuenca delivered and switched on 47 hearing devices, 11 of them cochlear implants, for 38 people who came from twelve Ecuadorian provinces.

Science and health · Pichincha

Quito physicist wins prize to map in 3D how the liver repairs itself

Hernán Morales Navarrete, who teaches at UDLA, was the only Latin American among the seven researchers the IBSA Foundation honoured in Barcelona.

Laws & agreements · Ecuador

Card payments in Ecuador: no surcharges, merchants paid in five days

Card payments in Ecuador: a new rule bans card surcharges and has merchants paid within five business days, with six months for the system to adapt.

Technology · International

Electric trucks now make up half of China's heavy-truck sales

In September, for the first time, more than half the heavy trucks sold in China were electric, driven by a growing network of battery-swap stations that can already replace a full battery pack in five minutes.

From other sections

Science and health · Pichincha

Quito physicist wins prize to map in 3D how the liver repairs itself

Hernán Morales Navarrete, who teaches at UDLA, was the only Latin American among the seven researchers the IBSA Foundation honoured in Barcelona.

Wellbeing · International

Daily iron for children: 114 studies, one clear benefit and several caveats

A Cochrane review published on 16 November pools 114 trials with 50,325 children. Daily iron reduces iron deficiency anaemia without more common infections, and the authors ask for local anaemia rates to guide decisions.

Ideas · International

The bear cave nobody will enter again, and what is gained by sealing it

A mountain guide found a cavity full of ancient bear bones in the Dolomites and reported it to the authorities, who sealed it. Plato, Aristotle and the psychology of awe help explain what someone gains by not keeping a discovery to themselves.

Laws & agreements · International

Three months, not nine years: the EU fast-tracks clean-energy paperwork

The European Parliament and the Council agreed in the early hours of November 18 to cap permitting times for solar panels, batteries and EV chargers at a few months, down from processes that can today drag on for nearly a decade.

Laws & agreements · Ecuador

Card payments in Ecuador: no surcharges, merchants paid in five days

Card payments in Ecuador: a new rule bans card surcharges and has merchants paid within five business days, with six months for the system to adapt.

Planet · International

UN documents 252 million hectares under restoration in 149 countries

A joint report by the FAO, UNEP and the Convention on Biological Diversity, unveiled at COP17 in Yerevan, documents 252 million hectares under some stage of ecological restoration across 149 countries, though it warns the pace must triple to meet the 2030 target.

Welcome to The Positive Way

Start your day with what's going right: progress, ideas worth thinking about and people who inspire. Because the world moves forward every day, and that deserves to be told.

Get only good news

Every morning, the best stories of the day in your inbox. Free, no noise, unsubscribe in one click.

Free until 1 June 2027. We only use your email for the newsletter and never share it.