174 machines and 26 plants in the pipeline: the world's fusion map keeps growing
The International Atomic Energy Agency now counts 174 fusion facilities worldwide, 40 more than in 2022, and a record $4.5 billion of private investment in a single year.

In 2022, the world's catalogue of fusion machines listed 134 facilities. This year it lists 174, counting those already running, those under construction and those still on the drawing board, according to a new report from the International Atomic Energy Agency (IAEA) launched in Vienna on 12 November.
The 128-page document is the fourth edition of the World Fusion Outlook. It was unveiled at the third high-level meeting of the World Fusion Energy Group, a forum the agency set up in 2024 so that governments, regulators, laboratories, companies and investors could work through practical questions together. Earlier editions were launched in London (2023), Rome (2024) and Chengdu (2025).
The story this year is one of scale. Fusion, the reaction that powers the Sun, has been a laboratory promise for some seventy years. The report describes a sector that now orders magnets in bulk, signs power purchase agreements and files requests to connect to the grid.
- Private fusion companies raised a record $4.5 billion in the twelve months to July 2026.
- Twenty-six fusion power plants are in the planning pipeline, eight of them aiming to deliver electricity in the early 2030s.
- Privately funded facilities have tripled since 2021 and now number 63.
- Two machines, one French and one Chinese, held stable plasmas for 1,337 seconds, more than 22 minutes.
- The report itself estimates the private industry may need a further $80 billion over two decades to reach the market.
At the heart of the report sits the IAEA's fusion facility database. Of its 174 entries, 111 are publicly funded and 85 of those are already operating, or 77%. The private machines number 63, but only 13 of them, or 21%, are running; the rest are still being built or designed. That gap captures the moment well. Private money arrived late and is now putting up its first hardware.
Geography tells its own story. According to a summary by the research network CASRAI drawing on the agency's data, Asia and the Pacific host 78 facilities, North America 53, Europe 38 and Latin America and the Caribbean just five.
On power plants, the report counts 26 fusion plant projects. According to the breakdown published by the American Nuclear Society, eight target electricity in the early 2030s, nine in the late 2030s, two in the 2040s and one in the 2050s. Six more have yet to name a date. The countries with plant concepts in development include Canada, China, Japan and South Korea as well as France, Germany, Sweden, Israel, New Zealand, Russia, the UK and the US, alongside the European Union as a bloc.
The money is arriving, and so are the buyers
Using figures from the Fusion Industry Association (FIA), the report puts new private investment over the past year at $4.5 billion, the highest annual total on record. Since 2021, the sector has drawn more than $14 billion according to the same survey.
The consultancy FusionX, which tracks 92 private fusion developers, offers a complementary view. Of those 92, 78 have already secured outside financing. If the current pace holds, it expects 2026 to close with around $7.6 billion raised, another record, as Nuclear Engineering International reported.
That spending may be the most tangible sign of change. This is no longer only about laboratories asking for budgets; it is about factories receiving orders. The report cautions, though, that the supply chain still has gaps and that capacity to manufacture many of the components at scale does not yet exist.
There are named customers, too. Commonwealth Fusion Systems, a spin-out from the Massachusetts Institute of Technology, plans its first commercial plant, ARC, a 400-megawatt facility in Chesterfield County, Virginia. Google and the Italian energy group Eni have agreed to buy more than half of its output, and the company has already applied to connect to the regional grid. Its demonstration machine, SPARC, in Devens, Massachusetts, is more than 80% complete and is expected to produce its first plasma in 2027.

Records inside the machines
Behind the investment figures lies physics that is moving forward. The report goes through the results of 2025 and 2026 facility by facility, and several numbers stand out.
The WEST tokamak, run by France's Alternative Energies and Atomic Energy Commission (CEA) at Cadarache, held a plasma for 1,337 seconds, just over 22 minutes. Over that time 2.6 gigajoules of energy were pumped into and removed from the chamber, under a magnetic field of 3.7 tesla. The CEA team announced the record in February 2025, and Chalmers University of Technology, which took part in the work, noted that the plasma sat at around 50 million degrees.
In China, a private machine matched that duration. Energy Singularity's HH70 tokamak, built with high-temperature superconducting magnets, sustained a stable discharge of 1,337 seconds during a campaign in late 2025. That the same number turns up at a public European lab and at a private Asian company sums up the report's argument neatly: the frontier is no longer pushed only by large state laboratories.

Germany's Wendelstein 7-X, at the Max Planck Institute for Plasma Physics, posted the best performance yet recorded for an optimised stellarator: a triple product, the figure that combines density, temperature and confinement time, of 1.1 × 10²⁰ sustained for 1.9 seconds. That puts it on a par with tokamaks of similar size. The machine had already made headlines this year with its 43-second high-performance plasma, and the report stresses that what limits it today is its heating hardware, not the physics.
In Madrid, the TJ-II stellarator at CIEMAT improved energy confinement by roughly 40% by firing several pellets of frozen fuel into plasmas heated with particle beams. In South Korea, the KSTAR tokamak held a high-confinement plasma for 102 seconds. And in the UK, MAST Upgrade became the first spherical tokamak to use coils that apply a three-dimensional magnetic field to tame the instabilities that batter its walls.
Lasers are contributing as well. The National Ignition Facility at Lawrence Livermore National Laboratory in California ran eleven experimental campaigns that crossed the threshold of scientific breakeven, releasing more fusion energy than the lasers delivered to the target. The record gain, above four, came in April 2025.
ITER, ahead of its schedule
The flagship international project, ITER, is still under construction in southern France. The report notes that it is running ahead of the reference schedule set in 2024. In June 2026 the sixth and final module of its central solenoid was installed, a step we covered at the time.
In China, assembly of the BEST tokamak in Hefei is speeding up: the report expects construction to finish by the end of 2027, with demonstrations of deuterium-tritium power generation around 2030. In Italy, the DTT facility at Frascati, designed to test how heat is drawn out of the plasma, is aiming for first plasma in the second half of 2032.

"The next phase of fusion will be defined not by progress in any one field but by the ability to bring together science, engineering, investment, regulation and international cooperation."
Rafael Mariano Grossi, IAEA Director General, in the report's foreword
What is still missing
The report is candid about the obstacles, and its authors put that in writing. In his foreword, Grossi reminds readers that moving from scientific achievement to commercially viable energy will take far more than capital: credible technical progress, manufacturing capacity, access to test facilities, sound regulation and trained people.
The financing gap is the most striking figure. In its core scenario, FusionX estimates that private industry will need roughly $80 billion more over the next twenty years to build pilot plants and the first commercial stations. Added to what is already committed, the total bill would come to about $100 billion.
Regulation is another open front. There is still no shared definition of a fusion power plant and no harmonised approach between countries, although several are acting. China wrote fusion into law for the first time in its Atomic Energy Law of September 2025. The UK is drafting a national policy statement that will, for the first time, give fusion facilities their own planning framework in England and Wales. Most regulators are leaning towards treating fusion differently from fission, because its risks are different: there is no chain reaction that can run away.
How much electricity it could supply
The outlook chapter, based on a study by the European consortium EUROfusion published in the journal Energy Strategy Reviews, avoids forecasts and sets out scenarios instead. Depending on the assumptions, fusion could supply anything from a few per cent to 15–20% of the world's electricity by the end of the century.
The study's most interesting finding is that the pace of deployment matters more than the date of the first plant. Arriving early counts for little if building then proceeds slowly. In its modelling, the reference cost for the first fleet of plants is around $6,000 per installed kilowatt, with a cheaper variant near $3,600.
That fits with what is already happening across the rest of the power system, where renewables overtook coal in 2025. If fusion arrives, it will plug into grids that have already changed a great deal, and it will have to find a place next to solar, wind and batteries, a point that other recent reports on emerging energy technologies also make.
Data to train the machines
This year's special chapter comes from Google DeepMind, the artificial intelligence lab that has already tested algorithms for steering the plasma inside a tokamak. Its essay argues that the bottleneck is not the algorithm but the data: decades of experiments stored in incompatible formats, undocumented archives and results that were never published.
According to CASRAI's summary, machine-learning surrogate models can cut some simulation times from weeks or months to hours, and controllers trained by reinforcement learning can adjust the coils in under a millisecond. The IAEA, for its part, is promoting an international fusion data lake so that results from different machines can be compared and reused.
"Building the right data foundations could prove as important as advances in AI itself."
Google DeepMind, in its contribution to the report, as quoted by Nuclear Engineering International
A detail you may have missed
WEST broke its own record within weeks. In the campaign that ended in December 2024, the machine had reached 824 seconds with 1.93 gigajoules of injected energy, according to the CEA. The next attempt almost doubled the time: 1,337 seconds, or 22 minutes and 17 seconds, on just 2 megawatts of heating and a plasma current of 215 kiloamperes. In computing slang, "1337" reads as leet, short for elite, and among programmers it is something of an in-joke. The number physicists care about is a different one, though: the 2.6 gigajoules the machine had to inject and then remove through its actively cooled tungsten components, the kind of part being tested for ITER.
The report closes on a note of caution and one of ambition. Grossi writes that fusion has always demanded ambition, and that it now needs something more: disciplined execution, credible evidence and cooperation. With 174 machines on the map, 26 plants in the pipeline and SPARC's first plasma due in 2027, the IAEA's next edition should have more results to report.
Further reading
- IAEA World Fusion Outlook 2026, the agency's full report.
- The Fusion Industry Association's summary of the Vienna launch.
- The WEST record explained by the CEA, with the parameters of the 1,337-second discharge.
- The FIA's private investment report, with the detail behind last year's $4.5 billion.
Go further
- Web · Organismo Internacional de Energía Atómica (OIEA)IAEA World Fusion Outlook 2026
El informe completo, con la ficha de cada máquina y los escenarios de EUROfusion hasta 2100.
YouTube · Kurzgesagt – In a NutshellFusion Power Explained – Future or FailureUna animación clara para entender por qué cuesta tanto encender una pequeña estrella en la Tierra.
YouTube · Cleo AbramNuclear Fusion, explained for beginnersLa física de la fusión contada desde cero, con visitas a laboratorios reales.
- Web · CEA-IRFMWEST sets a new plasma duration record
Los datos técnicos de la descarga de 1.337 segundos contados por el propio equipo del tokamak.
- Web · Chalmers University of Technology1337 seconds – the longest fusion experiment ever
La mirada de uno de los grupos europeos que participó en el récord de WEST.
- Web · Fusion Industry AssociationFusion industry attracts record annual funding of $4.48bn
De dónde salen los 4.500 millones de inversión privada del último año.
- Web · Nuclear Engineering InternationalIAEA maps future of global fusion
Un resumen técnico del informe, con las cifras de FusionX y la contribución de Google DeepMind.
Sources
- IAEA World Fusion Outlook 2026 (OIEA, noviembre de 2026)
- IAEA publishes 2026 World Fusion Outlook (American Nuclear Society, 13/11/2026)
- IAEA maps future of global fusion (Nuclear Engineering International, 13/11/2026)
- IAEA releases 2026 World Fusion Outlook (Fusion Industry Association, 12/11/2026)
- WEST sets a new plasma duration record (CEA-IRFM)