65 metres below the ships: Panama finishes the metro tunnel under the Canal
On 26 October 2026, the Line 3 boring machine reached Albrook after digging more than 4.5 kilometres in 25 months beneath the shipping channel. The monorail linking Panamá Oeste with the capital is due to open at the end of 2028.

On the morning of Monday 26 October 2026, in the extraction shaft at Albrook, right beside the Line 1 terminal of Panama City's metro, the cutting head of a machine almost 14 metres across was pushing through its last metre of rock. Behind it lay 25 months of work and more than 4.5 kilometres of tunnel running underneath the Panama Canal.
The tunnel boring machine, christened Panamá, set off in September 2024 from Farfán, on the western bank of the Canal, and finished its journey that Monday in Albrook, in the capital. Its arrival completed the excavation of the underground stretch of Metro Line 3, a monorail of roughly 25 kilometres that will link the city with the province of Panamá Oeste.
- The machine dug more than 4.5 km in 25 months, between Farfán and Albrook.
- At its deepest point it ran about 65 metres below mean sea level, beneath the shipping channel.
- The tunnel is lined with 2,295 concrete rings, each made of nine segments.
- Line 3 will have 11 stations and, according to Metro de Panamá, will cut the rush-hour trip from 90 to 37 minutes.
- Passenger service is expected to begin at the end of 2028.
Today the Panamá machine has managed, in a few minutes, with only one metre left, to complete 100% of the tunnel.
César Pinzón, general manager of Metro de Panamá

Sixty-five metres beneath the ships
Pinzón put it plainly to reporters gathered at Albrook, as Telemetro reported: the machine had passed under the Canal's channel at 65 metres below average sea level. Overhead, throughout those months, container ships, bulk carriers and cruise liners kept moving through the Pacific entrance, one of the busiest sea lanes on the planet.
The trickiest moment came in September 2025. On the 18th of that month, at the presidency's weekly press conference, Pinzón confirmed that the machine had crossed beneath the navigation channel and was heading towards Balboa, broadcaster TVN reported. By then it had excavated 2,046 metres, or 45% of the stretch.
In February 2026 it reached the Balboa evacuation shaft, roughly halfway along. It had bored more than 3.1 kilometres, fitted 1,560 rings and removed more than 800,000 cubic metres of material, according to Infobae. It stopped there for about three months of maintenance: an inspection of the cutter wheel, oil changes, electrical checks. More than a hundred workers, most of them Panamanian, rotated through three shifts so that digging never stopped, day or night.
The machine itself is a piece of German engineering. It was built by Herrenknecht, the company that also supplied the Line 1 machines, and cost around 45 million dollars, according to the newspaper Panamá América. It is roughly 93 metres long and its shield measures 13.51 metres in diameter. It uses a pressurised slurry system that holds up the excavation face as it advances, a technique explained in Wikipedia's entry on tunnel boring machines.
Every time the machine moved forward about two metres, it set in place a ring of nine precast concrete segments, made at a plant on the Vía Centenario. By the end there were 20,655 pieces.
From a bridge to a tunnel
The tunnel was never part of the original plan. Line 3 was supposed to cross the Canal on the fourth bridge, which would also carry road traffic. In 2020, faced with delays on that bridge and uncertainty over when it would be finished, the government decided to take the monorail underground.
That change came at a cost. The initial budget was around 2.8 billion dollars; it now exceeds 4.4 billion, Infobae reports, because of the excavation, ventilation, drainage and safety systems a tunnel at that depth requires. Officials argue that the underground route is safer in the long run and frees the monorail from depending on a separate project.
Construction is in the hands of the South Korean consortium HPH, made up of Hyundai Engineering & Construction and POSCO E&C, and the project is financed mainly through concessional loans from the government of Japan, channelled through the Japan International Cooperation Agency (JICA). Operating the boring machine was entrusted to a specialist Chinese firm, China Railway Tunnel Group.
X@TReportaVer publicación en X ↗For Panamá Oeste the project has a very daily meaning. Each morning about 160,000 vehicles cross the Bridge of the Americas and the Centennial Bridge, rising to around 174,000 in the afternoon, according to traffic-authority figures cited by La Prensa. The paper estimates that some commuters could save more than three hours a day on the round trip.
Metro de Panamá projects demand of 16,000 passengers at peak hour and about 160,000 a day, with trains less than four minutes apart. The line will start at Albrook, where it connects with Line 1, and run through Arraiján and Nuevo Chorrillo to Ciudad del Futuro. According to TVN, it will serve more than 500,000 residents of Panamá Oeste, and by 2025 it had already created more than 3,900 direct jobs.

What remains before the first ride
Reaching Albrook closes the hardest phase, not the project. Next comes dismantling the machine, installing the beams the monorail will run on, fitting the electromechanical systems and testing everything. Officials put overall progress at 82%, according to a tally by La República, and expect passenger service to begin at the end of 2028, after a trial run in the final months of that year.
The elevated section is further ahead. Trains are already running tests between Ciudad del Futuro and Vista Alegre, and the plan is to finish the overhead stretch in 2027. The timetable has slipped by more than a year compared with the original, and the planned fleet has gone from 28 trains to 26.
Once the monorail is running, the trip from Ciudad del Futuro to Albrook will take about 37 minutes, against the 90 that the Metro calculates for today's rush hour. It will be the first metro line to cross the Canal, with no need to sit in bridge traffic.
Panama has been piling up news around its waterway for months. In November the Canal returned to its maximum draught and added daily transits, and the country has passed laws such as its right to be forgotten for cancer survivors. Further south, in the Andes, Ecuador brought its Devil's Nose railway back into service after rebuilding five kilometres of track.

The detail you might not know
The boring machines used for Line 1 measured 9.77 metres across and went no deeper than 30 metres. The Panamá is almost four metres wider and went more than twice as deep.
What would happen to it afterwards was not clear from the start, either. In 2023 the Metro weighed three options: selling it, reusing it on other projects in the country, or even leaving it buried, because recovering it might cost more than it would be worth. A year later, President José Raúl Mulino suggested putting it to work on the future railway between Panama City and David, on the stretch from David to Santiago.
It is not the first tunnel of geological interest we have covered: in the Canary Islands, a lava tube under the sea off Lanzarote joined the world list of geological heritage sites. And for another side of the country, read how Panama's national crafts fair broke its sales record.
At Albrook, at the end of October, the machine that opened the way beneath the Canal came to rest about half a kilometre from the Line 1 platforms, where, in two years' time, the first passengers from Panamá Oeste should be stepping off.
Go further
YouTube · TVN NoticiasLínea 3 del Metro: tuneladora Panamá culmina su primera faseReportaje sobre la llegada de la tuneladora al pozo de Balboa, a mitad del túnel.
YouTube · Telemetro ReportaCulmina la construcción del primer tramo del túnel de la Línea 3 del Metro de PanamáImágenes desde dentro del túnel tras el cruce bajo el Canal.
YouTube · TVN NoticiasTuneladora avanza en las excavaciones de la Línea 3 del Metro de PanamáCómo trabaja la máquina y cómo se colocan los anillos de hormigón.
Sources
- Línea 3 – Metro de Panamá
- Línea 3 del Metro: tuneladora Panamá llega a Albrook – Telemetro
- Panamá termina la excavación del túnel bajo el Canal para la Línea 3 del Metro – La República
- Panamá completa túnel bajo el Canal para la Línea 3 del Metro – Infobae
- Línea 3 del Metro ajusta cronograma – TVN
- Línea 3 del Metro: cuánto falta para viajar en 37 minutos – La Prensa